Re: Avinor vil teste ut fjernstyrte kontrolltårn
ENHK mangler. Skulle vært i drift i 2020
ENMH mangler. Skulle vært i drift i 2022
ENNM mangler. Skulle vært i drift i 2022
Disse er også operative, kan se referanser til det i Visual Approach Chart, samt diverse lokale nyhetsartikler om man gjør et google-søk
Denne listen er korrekt:
https://avinor.no/en/remote
Implementation timeline for Remote Towers in Norway
Phase 1:
Røst - October 2019 (operational)
Vardø - October 2020 (operational)
Hasvik - November 2020 (operational)
Berlevåg - November 2020 (operational)
Mehamn – June 2022 (Operational)
Røros – June 2022 (Operational)
Rørvik – September 2022 (Operational)
Namsos – September 2022 (Operational)
Svolvær – January 2023 (Operational)
Sogndal – February 2023 (Operational)
Førde - February 2023 (Operational)
Molde - First half of 2025 (Planned)
Leknes - First half of 2025 (Planned)
Sandnessjøen - First half of 2025 (Planned)
Phase 2:
Order not determined.
Båtsfjord - 2026/2027 (Planned)
Mosjøen - 2026/2027 (Planned)
Sandane - 2026/2027 (Planned)
Sørkjosen - 2026/2027 (Planned)
Vadsø - 2026/2027 (Planned)
Ørsta-Volda - 2026/2027 (Planned)
New Mo i Rana airport - planned completion in spring 2027 (Planned)